On a Roseville panel job, the utility signs off first. Roseville Electric asks for its Electrical Panel Upgrade Application before anyone applies for the building permit, and the city's online permit process wants that written approval uploaded with the application.
Roseville Electric then tells the city itself. Its application page says you get a confirmation once the application is approved and the Building Department has been notified, and the city's procedure says the electric permit can be obtained after that approval reaches the Building Inspection Division.
What Roseville Electric actually wrote
Confirm the logo on the bill before anyone prices the job. The bold lines below are quoted from Roseville Electric's panel application page and from the city's panel replacement procedure, revised in April 2026.
Please allow up to 48 hours for Roseville Electric to review your application. That line is from Roseville Electric's application page. The city's procedure handout, revised 04/22/2026, says to allow three working days for completion of the approval form. Plan on the three working days.
Once the Building Permit has been issued, please schedule an electrical disconnect by contacting Roseville Electric Dispatch at (916)774-5620. The application page asks for 72 hours of notice before the panel comes out, and the handout says to call Dispatch three working days before construction. Both put the city building inspection on the same day as the disconnect.
Roseville Electric will require this green tag prior to setting your meter. The green tag comes from the city inspector, who the handout says comes out in the afternoon of the service change.
If the panel is getting bigger, the application page puts the conductors and conduit feeding it on the property owner, and warns that they may need to be upgraded at the applicant's cost to meet Building Code.
Neither page gives a power-off hour count for a residential swap.
Sagan's Roseville page warns that some homes with a Roseville mailing address sit in unincorporated Placer County, usually on PG&E and permitted by the county. That is a contractor field note.
Permits in Roseville
The Permit Center is at 311 Vernon Street, and Development Services takes appointment questions at 916-774-5285. A residential panel upgrade or replacement is one of the appointments the Permit Center books itself. Other building applications go to Building Plan Check.
Who pulls the permit matters. Sagan's Roseville page says that once the utility signs off, the shop pulls the permit through the city's online portal. On the morning of the swap, the handout says to call the Building Inspection Division at (916) 774-5332 between 7:30 and 8:00 a.m. and ask for your inspector.
A homeowner who does the panel work without a contractor's license is working under California's owner-builder exemption. CSLB's page for building officials, citing Business and Professions Code section 7044, says the exemption covers a principal residence only when the work is done before any sale, the homeowner has lived there for the 12 months before the work is finished, and it has not been used on more than two structures in any three-year period. Roseville's permit-process page is written partly for homeowners who pull their own permits. Call the Permit Center at 916-774-5285 to ask what an owner-builder application needs.
Price, without inventing one
Sagan's Roseville page leaves prices to its service pages. Its Sacramento panel page has an approximate table, permit included, built on typical Sacramento-area jobs rather than Roseville ones.
On that table, a same-amperage replacement such as a Zinsco or FPE swap is $2,000 to $3,500, and an overhead 100-amp to 200-amp service upgrade is $3,000 to $5,500. Peach Electric, a Sacramento shop that says it works with Roseville Electric, gives $2,500 to $10,000 for Sacramento-area panel work, from a sub-panel at the low end to a full main panel replacement at the top. Those two systems do not match. We will not average them. We are not inventing a Vernon Street midpoint from either system.
CSLB license 1050318 belongs to SAGAN ELECTRIC, a C10 Electrical contractor, and the license is current and active through 09/30/2027. The shop prints CSLB #1050318 on its Roseville page, which names Zinsco and Federal Pacific replacements and says the shop handles the Roseville Electric paperwork, the city permit, and the inspection. The CSLB record gives a North Freeway Boulevard address in Sacramento, and the Roseville page puts the shop "in Natomas, straight up I-80 from Roseville."
Sagan has no business arrangement with Panel Letter.
What to hand the carrier
A Roseville carrier packet starts with the closed City of Roseville electrical permit, the inspector's green tag or final on it, and an invoice that carries the C-10 number from that permit. Add photos of the old and new panel if the letter asks for them, and a load calculation or panel schedule only if the electrician wrote one. We found no California insurer page with a standard form for this, so ask your agent what the underwriter wants to see.
Typical replacement cost
Both bands here are Sacramento-area figures, one from the listed shop's own table and one from Peach Electric, and they disagree. We are not inventing a Vernon Street midpoint from them
$2,000 to $3,500
Same-amperage panel replacement, such as a Zinsco or FPE swap, on Sagan's Sacramento-area panel table, permit included
Sagan calls these approximate ranges, not quotes, based on typical Sacramento-area jobs. Its overhead 100-amp to 200-amp service upgrade row reads $3,000 to $5,500. Those two lines do not match. Peach Electric prints $2,500 to $10,000 for Sacramento-area panel work, sub-panel to full main panel. Those two systems do not match. We will not average them. We are not inventing a Vernon Street midpoint from either system.
Source: Sagan Electric$2,500 to $10,000
Peach Electric's Sacramento band, a sub-panel at the low end and a full main panel replacement at the top, from a shop that works with Roseville Electric
Peach says where a job lands depends mostly on the amperage and how much service entrance work comes with it. Sagan's same-amperage swap row is $2,000 to $3,500. Those two systems do not match. We will not average them.
Source: Peach Electric
Permit
City of Roseville Permit Center, Development Services
Who pulls it: The Permit Center is at 311 Vernon St., Roseville, California 95678, and Development Services answers appointment questions at 916-774-5285. Residential electrical panel upgrade replacement is one of the permit types the Permit Center books, apart from Building Plan Check. The Permit Center is open by appointment weekdays from 8:00 a.m. to noon and 1:00 p.m. to 4:00 p.m. All permit applications are submitted through the OPS Portal, and for a main panel replacement or upgrade the city wants Roseville Electric's written approval uploaded to the online application.
Who pulls the permit matters. Sagan's Roseville page says the shop handles the Roseville Electric application, the city permit, and the inspection. If another bidder says the same, ask whose name and which C-10 number go on the OPS application.
Utility coordination
What Roseville Electric and the city's panel procedure say
Who disconnects: Roseville Electric's panel upgrade application comes before the building permit. The application page allows up to 48 hours for review, and the city's procedure handout, revised 04/22/2026, allows three working days. After the permit is issued, the disconnect is booked with Roseville Electric Dispatch at (916)774-5620, on 72 hours' notice by the application page and three working days by the handout, and the city inspection goes on the same day. Roseville Electric needs the inspector's green tag before it sets the meter.
Outage window: Roseville Electric does not publish a guaranteed power-off hour count for a residential panel swap.
Confirm the logo on the bill before anyone prices the job. Sagan's Roseville page says most of Roseville gets its power from Roseville Electric, not SMUD or PG&E, and that some homes with a Roseville mailing address sit in unincorporated Placer County, usually on PG&E and permitted by the county. That is a contractor field note.
What to hand the insurer
- Closed City of Roseville electrical permit
- The inspector's green tag or final on that permit
- Invoice showing the California C-10 license used on the permit
- Photos of the old and new panel if the carrier’s letter asks for them
- Load calculation or panel schedule if the electrician produced one
Ask your agent for the exact list. Carriers do not publish a single national checklist.
Electricians who advertise this job
A shop is listed only if it advertises Federal Pacific, Zinsco, or insurance-driven panel replacement on its own site and prints a license number there. Trade-association locators already exist. We will not pad this list. Verify the license before you hire.
To get introduced, use the quote form on this page. We do not send you to the shop from here.
Sagan Electric
Sacramento, CA
Published license: 1050318 (California Contractors State License Board)
Own Roseville page that names Zinsco and Federal Pacific replacements and the Roseville Electric application, city permit, and inspection, backed by CSLB #1050318 printed on the shop’s own site.
How this page was built
Compiled by Panel Letter on 2026-10-20 from the public pages below. If a fact was not on a cited page, it is marked as unverified in the copy. This is a research guide, not a bid.
- Sagan Electric, Electrician in Roseville, CA
Prints CSLB #1050318. 100A to 200A upgrades, Zinsco and Federal Pacific replacements. We handle the Roseville Electric paperwork, the city permit and the inspection. Most of Roseville gets its power from Roseville Electric, the city-owned utility, not SMUD or PG&E. Some homes with a Roseville mailing address sit in unincorporated Placer County. Those are usually on PG&E and permitted by the county instead. Our shop is in Natomas, straight up I-80 from Roseville. Once the utility signs off, we pull the permit through the city's online permit portal. No panel dollar band on the page. Our service pages list approximate ranges for panel work, EV chargers and repairs.
- Sagan Electric, Home and contact pages
CSLB License #1050318. 4234 N Freeway Blvd #300, Sacramento, CA 95834. Based in Natomas, serving the greater Sacramento region, Roseville included. Public shop mailbox is on this page. The homepage price table lists outlets, ceiling fans, and dedicated 240V circuits, with no panel price.
- CSLB, License 1050318
Official lookup. SAGAN ELECTRIC, 4234 N FREEWAY BLVD 300, SACRAMENTO, CA 95834. This license is current and active. Classification C10 ELECTRICAL. Issue 02/19/2019. Reissue 09/19/2023. Expire 09/30/2027. Data current as of 10/20/2026 6:25:53 PM.
- Sagan Electric, Panel upgrade and replacement in Sacramento
Approximate Sacramento-area ranges for panel work (permit included). Panel replacement, same amperage (e.g. Zinsco or FPE swap) $2,000 to $3,500. Service upgrade 100A to 200A, overhead service $3,000 to $5,500. These are approximate ranges, not quotes. They're based on typical Sacramento-area jobs. Sagan Electric pulls the permit, coordinates the shutoff with SMUD, PG&E or Roseville Electric, and meets the inspector. Prints CSLB #1050318.
- Peach Electric, Electrical panel upgrades
Panel work in the Sacramento area runs from about $2,500 for a sub-panel to $10,000 for a full main panel replacement. Where your project lands depends mostly on the amperage you're moving to and how much service entrance work comes with it. Roseville Electric and PG&E run their own versions of the same process, and we work with all three week in and week out. 333 University Ave, Sacramento. Prints CSLB C-10 Electrical Contractor License #1105424. Cost source only here.
- City of Roseville, Schedule an Appointment with Development Services
Schedule an Appointment with Permit Center for residential electrical panel upgrade replacement. All other Building applications go to Building Plan Check Services. Call 916-774-5285. 311 Vernon St. Roseville, California, 95678.
- City of Roseville, Online Building Permit Process
Permit Center and Appointment Hours Monday through Friday 8:00 am to noon, 1:00 pm to 4:00 pm. All permit applications are submitted electronically through our OPS Portal. Electrical service main panel replacement or upgrade: written approval from Roseville Electric must be uploaded to the online application. Maybe you're a homeowner who has decided to obtain your own building permits.
- Roseville Electric, Electrical Panel Upgrade Application
Please complete this application before applying for a Building Permit. Please allow up to 48 hours for Roseville Electric to review your application. You will receive confirmation once the application has been approved and the City of Roseville Building Department has been notified. Once the Building Permit has been issued, please schedule an electrical disconnect by contacting Roseville Electric Dispatch at (916)774-5620. Please provide a 72-hour advance notice of when the panel replacement will occur. Please schedule your City of Roseville Building Inspection the same day as the electrical disconnect. The property owner is responsible for the conductors and conduits providing service to the electrical panel. In the event the panel is being upgraded to a larger size, the conduit and conductors may not meet Building Code and will need to be upgraded at the applicant's cost.
- City of Roseville, Residential Electric Service Upgrade/Panel Replacement Procedure (revised 04/22/2026)
Prior to applying for your Building Permit you will need to contact the Roseville Electric New Service Division. Please allow three working days for completion of approval form. After Roseville Electric approves the electric panel location / service, they will send the location and approval to the Building Inspection Division. Then you can obtain an electric permit from the Building Inspection Division, located at the Civic Center, 311 Vernon Street. Contact Roseville Electric Dispatch to schedule the Disconnect/Reconnect three working days prior to construction at (916)774-5620. The morning of your service change call (916) 774-5332 between 7:30AM and 8:00AM and ask to speak to your inspector. We will make arrangements to come out in the afternoon to perform the inspection and issue you a green tag. Roseville Electric will require this green tag prior to setting your meter.
- CSLB, Owner-Builder Overview for building officials
A homeowner improving their principal place of residence is exempt from licensure if all of the following exist: the work is performed prior to sale, the homeowner resides in the residence for the 12 months prior to completion of the work, and the homeowner has not taken advantage of this exemption on more than two structures during any three-year period. For more information regarding owner-builder, see Section 7044 of the Business and Professions Code.
- CSLB, Check a license
Official California contractor-license lookup.