Carriers in Oklahoma City still flag Federal Pacific, Zinsco, and Pushmatic. Wanner’s panel page calls them obsolete hardware. Alliance’s upgrade page says Federal Pacific needs a look before anyone prices a swap. Your insurance letter is usually written somewhere else. Permits run through the Development Center. On most bills the meter belongs to OG&E.
Those two systems do not match. The city issues the electrical permit. OG&E will not treat an unannounced meter pull as ordinary maintenance. A helper with a van is not the person who can print that permit or get the inspection report to OG&E.
What OG&E actually wrote
Start with the U760 metering guidelines. No customer or their agent shall access the utility equipment of OG&E. The same page says the National Electric Safety Code prohibits access to utility equipment by anyone other than the utility. That list includes self-contained meter bases.
The construction-services FAQ is the restore rule. An inspection is required any time OG&E disconnects service for an electrical contractor to work on the electric equipment. The inspection report must be sent to OG&E directly from the inspecting authority. That is not a homeowner meter-pull path.
Confirm the logo on the bill. Most Oklahoma City addresses are OG&E. Edmond Electric and some other municipal systems are a different ticket.
OG&E does not publish a guaranteed power-off hour count. Alliance describes timing as depending on scope, utility coordination, and inspection. That is a contractor field note.
Permits inside Oklahoma City and in the nearby towns
Inside the city, start at the Development Center, first floor of 420 W. Main Street. Filing is Accela Citizen Access. Trade questions go to (405) 297-2948.
Who pulls the permit matters. The Development Center FAQ is a closed list. Electrical permits may only be issued to contractors licensed in the State of Oklahoma and registered as required by the City of Oklahoma City. The same page says all electrical work must be done by those contractors. A permit has to be issued before the work starts. There is no owner-occupant electrical-permit path on those pages.
Edmond, Moore, Yukon, and Norman file at their own counters. A quote that only says “we handle the permit” should name the city on the address.
Price, without inventing one
Alliance’s Oklahoma City panel page publishes two planning ranges and does not hide the spread. A straightforward panel replacement, where the existing service size stays usable, is printed at $2,500 to $4,500. A 100-amp to 200-amp service upgrade on that same page is $4,500 to $7,500+. Those two systems do not match. We will not average them. We are not inventing a third Oklahoma City midpoint from either row.
Oklahoma license lookup is public. Ask for the CIB number and check it on the Construction Industries Board before you sign. For a city address, also ask for the city registration they will put on the Accela file. Two shops advertise this work on their own sites and print a license number. Wanner’s panel page names Federal Pacific, Zinsco, and Pushmatic and prints 003613. Alliance’s panel page names Federal Pacific and prints 009783. They write daily work across Oklahoma City, Edmond, Yukon, Moore, and nearby towns. They are listed for the panel letter, not as an Oklahoma County directory.
Directory-only shops are omitted. A page that names these brands and does not print an Oklahoma electrical license number is not a listing. The listed shops are not affiliated with Panel Letter.
What to hand the carrier
The useful packet is the closed city or suburban electrical permit, the passed inspection, proof the inspecting authority sent the report to OG&E, an invoice with the license number that was on the permit, and photos if the letter asks. If your electrician produces a load calculation or panel schedule, send that too. We did not find a carrier page that publishes a single statewide sticker form. Ask the agent what they will actually open.
Typical replacement cost
One Oklahoma City shop publishes two panel bands that do not describe the same job
$2,500 to $4,500
Planning range for a straightforward residential panel replacement where the existing service size and surrounding equipment remain usable
Their Oklahoma City panel-upgrade page. They call this a planning range, not a quote. We are not inventing an OKC midpoint from this band.
Source: Alliance Electric Services$4,500 to $7,500+
Planning range for a 100-amp to 200-amp service upgrade that may involve meter or service equipment, conductors, grounding, permits, inspection, and utility coordination
A different row on the same page. A service-capacity upgrade is not a same-size panel replacement. Those two systems do not match.
Source: Alliance Electric Services
Permit
Who pulls it: The Development Center FAQ says electrical, plumbing, and mechanical permits may only be issued to contractors licensed in the State of Oklahoma and registered as required by the City of Oklahoma City. The same page says all electrical, plumbing, and mechanical work must be done by those contractors, and a permit must be issued prior to starting any work. There is no owner-occupant electrical-permit path on that page.
Edmond, Moore, Yukon, and Norman file at their own counters. A quote that only says we handle the permit should name the city on the address. Oklahoma electrical-contractor licensing is the Construction Industries Board. The city also wants its own contractor registration. Ask for the CIB number they will put on the Accela file.
Utility coordination
OG&E on most Oklahoma City bills
Who disconnects: OG&E’s U760 metering guidelines say no customer or their agent shall access the utility equipment of OG&E. The same page says the National Electric Safety Code prohibits access to utility equipment by anyone other than the utility, including self-contained meter bases. OG&E’s construction-services FAQ says an inspection is required any time the company disconnects service for an electrical contractor to work on the electric equipment. The inspection report must be sent to OG&E directly from the inspecting authority. That is not a homeowner meter-pull path.
Outage window: OG&E does not publish a guaranteed power-off hour count for a residential panel swap.
Confirm the logo on the bill before anyone prices the job. Edmond Electric and some other municipal systems are not this book. A like-for-like panel swap still needs the OG&E disconnect and the Development Center inspection.
What to hand the insurer
- Closed Oklahoma City or suburban electrical permit
- Passed Development Center or suburban inspection, with the report sent to OG&E
- Invoice showing the Oklahoma CIB license used on the permit
- Photos of the old and new panel if the carrier’s letter asks for them
- Load calculation or panel schedule if the electrician produced one
Ask your agent for the exact list. Carriers do not publish a single national checklist.
Electricians who advertise this job
A shop is listed only if it advertises Federal Pacific, Zinsco, or insurance-driven panel replacement on its own site and prints a license number there. Trade-association locators already exist. We will not pad this list. Verify the license before you hire.
To get introduced, use the quote form on this page. We do not send you to the shop from here.
Wanner Electric
Oklahoma City, OK
Published license: 003613 (Oklahoma Construction Industries Board)
Oklahoma City panel-upgrades page that names Federal Pacific, Zinsco, Pushmatic, and fuse boxes and prints Oklahoma Electrical License 003613.
Alliance Electric Services
Oklahoma City, OK
Published license: 009783 (Oklahoma Construction Industries Board)
Oklahoma City panel-upgrade page that names Federal Pacific evaluations and prints Oklahoma Electrical Contractor License 009783.
How this page was built
Compiled by Panel Letter on 2026-09-12 from the public pages below. If a fact was not on a cited page, it is marked as unverified in the copy. This is a research guide, not a bid.
- Wanner Electric LLC, Panel upgrades
Names Federal Pacific, Zinsco, Pushmatic, and fuse boxes. Prints Oklahoma Electrical License 003613. Public shop email is on this page.
- Alliance Electric Services, Electrical panel upgrades in Oklahoma City
Names Federal Pacific. Prints License 009783. Prints $2,500 to $4,500 for panel replacement and $4,500 to $7,500+ for 100-amp to 200-amp.
- City of Oklahoma City, Development Center
Electrical permits issued only to state-licensed contractors registered with the city. Homeowners may not do the electrical work themselves.
- City of Oklahoma City, Building and trade permits
State CIB licensing plus city contractor registration. Trade permits file through Accela or the Business Center at 420 W. Main St.
- OG&E, Construction services FAQs
Inspection required when OG&E disconnects for contractor work. The inspecting authority must send the report to OG&E.
- OG&E, U760 metering guidelines
No customer or their agent shall access OG&E utility equipment, including self-contained meter bases.
- Oklahoma Construction Industries Board, Licensee search
Official Oklahoma electrical-contractor lookup.